Lufhereng Development Company (Pty) Ltd
Luferenge Housing Development, Protea Glen, Soweto, Gauteng, South Africa
Start Date: 28 June 2019
End Date: 31 March 2021
Raubex Infra Project Manager: | Cornel Strydom |
Raubex Infra Contract Manager: | Daniele Carnicelli |
Raubex Infra Construction Manager: | Nikki Carnicelli |
Engineer: | Bigen Africa |
| Andre Wesson |
Resident Engineer: | Sikho Sikhosana |
Project Value (Incl. Vat) | R181 510 639,94 |
Scope of Works: | |
Nature Of Works:Civil Engineering Services – Roads, Stormwater, Sewer and Water Infrastructure for Lufhereng Ext 7 | |
The Works Include: | |
| |
Quantity Indicators | |
Roads: Clear & grub 102 000m² Earthworks 50 000m³ Layerworks (roadbed, subbase & base) 30 000m³ Kerbing 14 km Paving 3 200m² Asphalt 41 844m² Pipeworks: Site clearance (all works) excavation 19 680km HDPE pipework (cable, ducts, sewer and water) 19 680km Electrofusion erf connections (sewer and water) 544Stands Stormwater pipes (various pipes spigot & socket) 3.2km Kerb inlets/junction boxes 158 no. | |
Concrete Structure: Earthworks (Channels & Concrete Structures) 34 000m³ Culvert Various Sizes 2.4km Steel Re-Enforcing 450Ton Concrete Volume (Various Specs) 4 100m³ | |