Back to Projects

Scatec Solar SA 163 (Pty) Ltd
Construction of a 75MW PV Farm near Burgersdorp, Eastern Cape
Start Date: 12 May 2018
End Date: 12 April 2018


Project Details


PROJECT MANAGERS:
Scatec: Mr Dermott Murphy
Raubex Infra: Mr Donovan de Sousa
Cell:0817642850
Email: Donovan.d@raubex.com
ENGINEER
None
RESIDENT ENGINEER
N/A


CONTRACT MANAGER
Mr Charles Deacon
Tel: 051 406 2000/ 082 496 2629
E-Mail: Charles.d@raubex.com
SITE AGENT
Mr Stefan Theron
Tel: 082 417 6781
Email:Stefan.t@raubex.com


CONTRACT INFORMATION:

DATE OF AWARD

REVISED

DATE OF AWARD

5 June 2013


COMPLETION DATE

24 July 2014


VALUE (INCL VAT)

R136,800,000

R141,781,233.72

CONTRACT PERIOD
                     8 Months

12 Months





THE WORKS INCLUDE:
Site Preparation, construction of 1km access road, erection of 10km electrified perimeter fence, internal service roads, trenches, storm water management, construction of O&M building
Solar stringing of homerun cables, installation of string monitors, inverters and transformer stations with associated cabling for 840V DC system as well as 22kV MV system to main 22/132kV substation.
Installation of communication network and weather stations with communication to control room.

QUANTITY INDICATORS (AS BILLED IN TENDER DOCUMENT):


TRENCH EXCAVATION

 14500 M³

MASS EARTHWORKS

  50000M³

LAYERWORKS

                                                       15000 M³

EXCAVATION TO ACCESS,SLABS AND DRAINAGE

                                                                                1200 M³

DOUBLE SEAL ASPHALT SURFACING
MASS CONCRETE (BASES AND DRAINAGE)
CABLES & CONDUITS

                                                   0) MM

0 M³

1255170 M

CABLE LAYING
MODULES INSTALLED

1255170 M

256000


Construction of a 75MW PV Farm near Burgersdorp, Eastern Cape


© Raubex Infra 2025 . All rights reserved. Website design & development by DIGITAL PLATFORMS.
Division of the Raubex Group of Companies.
Click here to visit the Raubex Group Website
footer_logo